What Is a Pipe Gallery Trolley?
A pipe gallery trolley is a movable steel formwork system used to cast the walls and roof of underground utility tunnels — the “pipe galleries” that carry power, telecommunications, water supply and drainage lines beneath modern cities. Because a utility tunnel is built segment by segment in a narrow excavation, conventional loose formwork is slow and labor-hungry. A pipe gallery trolley solves this by integrating the formwork system and the trolley gantry into one unit: once assembled, the formwork is erected and stripped without dismantling, simply by turning the trolley’s adjusting spindles or activating its hydraulic lifting system. The result is a safe, fast, repetitive casting rhythm — one standard segment per cycle.
Figure 1 – A pipe gallery trolley standing in a completed utility tunnel segment, side formwork in the erected position.
Structure and Main Components
Typical models, such as the TC-120 pipe gallery trolley system developed by Lianggong Formwork, consist of the following parts:
| Component | Function |
| Top formwork and side formwork (steel or timber) | Contact face for the cast concrete; defines the tunnel cross-section |
| Gantry (portal frame) | Backbone of the trolley; receives all concrete loads through the support system |
| Formwork cross braces and diagonal braces | Lock the formwork into position and stiffen it against fresh-concrete pressure |
| Hydraulic lifting system | Raises and lowers the formwork during erection, stripping and height adjustment |
| Adjusting supports | Transfer trolley loads to the traveling trough and fine-tune vertical position |
| Traveling wheels (manual, electric or hydraulic) | Move the whole trolley forward to the next casting segment |
Formwork panels come in two families. A steel panel system uses a 6mm steel plate with [8 channel-steel secondary joists and double [10 channel-steel main joists, bolted on the side. A timber panel system pairs an 18mm imported WISA board with H20 timber beams as secondary joists and double [12 channel steel as main joists — the same H20 beam technology Lianggong applies across its H20 timber beam formwork systems.
Figure 2 – Labeled cross-section: top formwork, gantry, cross and diagonal braces, adjusting support, bottom limiter, traveling wheel (electric motor available) and hydraulic lifting system.
Load Path and Working Principle
The design logic is simple and efficient: all loads produced by the fresh concrete pass through the formwork and its support system into the trolley gantry, and from the gantry through the extended adjusting supports down to the traveling troughs laid on the base slab, and finally into the ground. The hydraulic lifting system is used only for adjustment — it does not carry construction loads — which protects the hydraulics and keeps the structure rigid and safe throughout the pour.
Assembly Process on Site
Field assembly of a pipe gallery trolley follows a fixed sequence:
1. Check all delivered components against the packing list.
2. Prepare the working area — the invert and both connection walls are cast first, with the trolley formwork overlapping 100mm down the walls.
3. Lay the traveling troughs ([16 channel steel) on the floor and connect the bottom longitudinal beams with the adjusting supports, traveling wheels and hydraulic system.
4. Erect the gantry on the bottom beams.
5. Connect the top longitudinal beams and hang the top and side formwork.
6. Install the formwork cross braces and gantry diagonal braces.
7. Fit the hydraulic power pack and electric traveling motors, fill 46# hydraulic oil and connect the wiring.
8. Test: hydraulic cylinders, lifting system, oil leakage, motor rotation and wheel travel.
9. Hand over for acceptance and sign-off before first use.
The Standard Casting Cycle
Once accepted, each segment follows the same ten-step rhythm: move the trolley into position and level it (four sets of traveling wheels per unit, front and rear pairs in the same trough — leveling by driving one side only); lift the hydraulic system, extend the adjusting supports onto the troughs, then retract the hydraulics; adjust the cross braces and set the side formwork to position (panel alignment tolerance within ±5mm per unit); fix the gantry diagonal braces; fix the roof rebar; pour the segment after inspection; during curing, prepare the next unit's wall rebar; after the concrete reaches design strength, remove the diagonal braces and strip the cross braces; lift the trolley, retract all adjusting supports, lower the wheels back to the floor and lay the troughs for the next segment; travel to the next unit and repeat. In practice the formwork erection for one standard segment takes about half a day, so a well-organized crew can close the loop segment after segment with a small team.
Figure 3 – Workers erecting the side formwork of the trolley; assembly is completed once and repeated without dismantling.
Safety and Maintenance Essentials
Travel moves must be supervised by dedicated spotters at the front, rear, sides and top, under a single command signal, and the trolley must never be dragged or forced. Traveling troughs are set out by line and anchored to the slab, and the travel path must be clean and level. Power and lighting cables are insulated, suspended and kept off the floor and out of water. Concrete is poured symmetrically with a level difference of no more than 0.6m between the two walls to avoid eccentric loading, with pouring speed controlled against float-up. For maintenance: a dedicated person inspects the trolley monthly — member deformation, loose or missing bolts and pins, circuit integrity, cylinder and hose leakage — replaces hydraulic oil every six months, and keeps motors dry and pivot points greased. Operators are trained, examined and fixed to their posts.
Choosing a Configuration
Semi-automatic trolleys travel by pulling devices such as a winch; fully automatic trolleys carry electric traveling wheels and move forward or backward at the push of a button. Steel panels favor reuse and stiffness on long alignments; timber panels favor cost and quick adaptation. If your alignment also involves curved or arched sections, Lianggong's experience with hydraulic formwork systems and the tunnel formwork solutions page show how the same engineering logic extends beyond straight box sections. For a configuration matched to your cross-section and casting rhythm, send your drawings through the contact page for a tailored proposal — or start with the commercial overview in TC-120 Pipe Gallery Trolley: Faster, Leaner Utility Tunnel Construction.
Frequently Asked Questions
What is a pipe gallery trolley used for?
It casts the walls and roof of underground utility tunnels (pipe galleries) segment by segment, replacing loose formwork with an integrated, reusable steel trolley and formwork unit.
How fast can one segment be formed?
In normal site conditions, formwork erection for one standard segment takes about half a day; the full cycle (level, lift, rebar, pour, cure, strip, travel) repeats segment after segment without dismantling the system.
Which formwork panels should I choose, steel or timber?
Steel panels (6mm plate with channel-steel joists) maximize stiffness and reuse on long alignments; timber panels (18mm WISA board with H20 beams) favor cost and quick adaptation on shorter runs.
What is the difference between semi-automatic and fully automatic traveling?
Semi-automatic trolleys are pulled forward by a winch or similar device; fully automatic trolleys carry electric traveling wheels and move forward or backward at the push of a button.
What maintenance does the trolley need?
A dedicated person inspects it monthly — member deformation, bolts and pins, circuits, cylinder and hose leakage — hydraulic oil is replaced every six months, and motors must stay dry with pivot points kept greased.
Can the trolley be adapted to my cross-section?
Yes. Panel systems and gantry spacing are configurable, and non-standard geometry can be handled through customized steel moulds.
Company: Yancheng Lianggong Formwork Co., Ltd.
Website: https://www.lianggongformwork.com https://www.fwklianggong.com https://lianggongform.com
Email: sales01@lianggongform.com
Tel: +86-18201051212
Address: No.8 Shanghai Road, Jianhu Economic Development Zone, Yancheng City, Jiangsu Province, China
Contact our engineering team for a free trench shoring quotation →
Post time: Nov-18-2026